Estimating project progress:
By 21 December 2019 29%
By 20 December 2020 45%
By 21 December 2021 69.2%
Subsidiary company:
Iron and Steel Ghadir Iranians
Project cost estimate:
141 million euros
About the project:
Construction of an iron pellet production unit from the Chadormelo factory concentrate with an annual capacity of 4 million tons that can be used in direct reclamation factories for the production of sponge iron in order to be profitable and also to ensure the availability of feed for the holding's downstream industrial units.